Task Acquisitions CapEx RAM / PM GPs Finance Investor Relations
Phase 1 — Initiation Day 0
Contract executed; DD clock starts R · A II III
Open deal-specific Slack channel R · A II III
Deal channel comms protocol
Any 1:1 conversation affecting scope, rents, pricing, or timing requires a written summary posted to the deal channel within 24 hrs. All parties responsible for their own summaries.
R · A · owns postsposts postspostsposts
Viability target communicated to CapEx + RAM
Includes CapEx budget target and projected rents by market.
Master Pricing Sheet
R · A II I
Ensure receipt of all DD documents and review
Exhibit C required in Excel format. Confirm all items received; flag gaps immediately.
R · A
Request insurance + landscaping quotes from preferred vendors R · A C I I
Phase 2 — Data Intake & Prep Day 1–2
Data formatting — structure all DD docs to UW-ready format R · A
Data extraction — pull key financials, unit mix, expense data R · A
Share leases with PM team for full lease audit A · delivers R · owns audit
Phase 3 — Initial UW Build + Day 5 Sync Day 3–5
Complete initial underwriting
Hard deadline: 72 hrs from DD start
R · A I
Full-unit onsite walkthrough — RAM + CapEx required
Schedule at LOI to provide 2–3 weeks notice. Complete by Day 5.
A · schedules R · onsite R · onsite I
Day 5 budget sync Day 5
GP John Crowell · GM of RAM · Acquisitions · Initial UW + preliminary budget reviewed together
R · facilitates C A · required A · required
Phase 4 — CapEx Budget + UW Refinement Day 5–10
Detailed CapEx budget finalized using master pricing sheet + reno packages
Apply L1/L2/L3 reno package per unit type. Exterior items, MEP replacements, and per-room costs broken out clearly. Hard deadline: Day 10.
C · receives R · A · owns
UW model updated with confirmed CapEx inputs + lease audit findings R · A C C · audit
Proforma + business plan draft shared with all parties for pre-sync review R · A reviews reviews reviews
Scope changes posted to deal channel with written team summary posts posts posts posts
All-party alignment sync Day 10 — Mandatory
Final proforma, reno scope (L1/L2/L3), and rent projections confirmed as a team. Open items assigned and posted to deal channel. No proxy sign-off accepted.
R · facilitates A · required A · required A · required I
Phase 6 — Final Review + Revisions Day 11–13
Address revisions to scope, rents, or pricing from Day 10 sync R · A R R R
Financing package assembled — proforma, deal overview, and financials R · A C
All-party sign-off — final proforma + renovation plan Day 14 — Hard Deadline
Written confirmation required from all parties. No exceptions. Enables lender package release.
A · collects signs signs signs
Phase 8A — Finance: Lender Package Day 14
Lender-ready UW package sent to loan broker — immediately following sign-off R · A · sends I
Phase 8B — Investor Relations: Handoff Day 14
IR handoff packet delivered — deal overview, proforma, business plan R · A · prepares R · receives
OM + capital raise materials — IR-led with Marketing support C C R · A · owns
Key Acquisitions CapEx / RAM / PM Milestone sync Sign-off deadline R = Responsible  ·  A = Accountable  ·  C = Consulted  ·  I = Informed